Contractor finds asbestos while repairing bridge

By Patricia Mazzei, http://www.miamiherald.com

Walter Michot / Miami Herald

Walter Michot / Miami Herald

A contractor repairing the bridge that connects Virginia Key to Key Biscayne has found asbestos on a tube containing electrical wiring for street lights – an unforeseen condition that could delay the project’s completion.

Kiewit Infrastructure found the asbestos when it demolished a portion of the Bear Cut Bridge’s roadway in August, according to a memo Miami-Dade Mayor Carlos Gimenez sent county commissioners Friday. The company has been removing and disposing of the tainted material.

The extra work could push back the repairs by several weeks, according to the memo. Kiewit has claimed a 36-day delay, though the county is still negotiating that number.

As part of bonds scheduled for commission approval in December, $750,000 in funding would be set aside to handle the asbestos. The final costs of the fix are still being negotiated. Read More

 

Advertisements

About quantem labs

Environmental and Food testing services and information. Serving the Oklahoma City area and beyond. Call to find out how we can help you with your samples 1-800-822-1650

Posted on December 9, 2013, in Asbestos, Remediation/Renovation and tagged , , . Bookmark the permalink. Leave a comment.

Leave a Reply

Fill in your details below or click an icon to log in:

WordPress.com Logo

You are commenting using your WordPress.com account. Log Out / Change )

Twitter picture

You are commenting using your Twitter account. Log Out / Change )

Facebook photo

You are commenting using your Facebook account. Log Out / Change )

Google+ photo

You are commenting using your Google+ account. Log Out / Change )

Connecting to %s

%d bloggers like this: